Most preliminary bio-mining works at Kodungaiyur dump yard to be...
It would take at least 2 years to retrieve the original land at Kodungaiyur dump yard. The bio-mining project is carried out in six packages divided...
‘Restore Kodungaiyur, Perungudi dump yards as wetlands’
Kodungaiyur residents echoed the sentiments of Perungudi residents, who wanted the Greater Chennai Corporation to reclaim the marshland and restore it...
Rs 648 cr for biomining Kodungaiyur dumpyard
The GCC will pay for the cost of engaging PMC.
Clean the dump, GCC
Singara Chennai 2.0 may be one of the goals of the State government, but reality is quite contrary to the vision, especially considering given the...
Waste-to-energy plant to come up at Kodungaiyur dump yard
“After discussing the proposal with Chief Minister MK Stalin, we will implement the same at Kodungaiyur dump yard because the residents suffer from...
Corporation to ready feasibility report to reclaim Kodungaiyur dump...
The Greater Chennai Corporation has decided to prepare a feasibility report to implement land reclamation project in Kodungaiyur dump yard, which...
Minor fire in Kodungaiyur dump yard
Fire engines from nearby fire stations and water tanker lorries were deployed to contain the fire. The fire was due to high temperature.
7.5 MT CO2 emission prevented through biomining in Perungudi dump yard
The bio-mining work started on October 12, 2022, with an estimated cost of Rs 350 crores. The contract tenure of the project is three years, and the...