Vellore airport opening to be delayed by 4 months for want of more land
The long-awaited opening of the Vellore airport is likely to be delayed by another four months as the Airports Authority of India (AAI) has asked for additional lands to ensure a safety strip at the end of the newly laid runways.
Vellore
Official sources said that the facility was started under the UDAN RCS (Ude Desh ka Aam Naagrik Regional Connectivity Scheme) of the Central government and it should have got off the ground more than a year ago. However, it was delayed due to the pandemic and connecting of the runway and the terminal building located on either side of the Abdullapuram–Asanambut Road.
Finally, the Asanambut Road was blocked and the perimeter road laid due to which traffic plied unhindered, officials added. Subsequently, Vellore district officials were taken by surprise as airport officer in charge Meghanathan, while taking part in a meeting chaired by then Collector A Shanmuga Sundram, requested for an additional 11 acres.
Asked about the airport’s present status, AAI Chennai regional executive director R Madhavan said, “We have asked for 10.82 acres at the end of the runway to ensure total safety. Once the land is handed over we will start the tender process to finalise work, all of which will consume three months, after which the facility will apply to DGCA for operational licence.”
Visit news.dtnext.in to explore our interactive epaper!
Download the DT Next app for more exciting features!
Click here for iOS
Click here for Android
Next Story